Completed
This project is a classroom addition with underground parking, satellite kitchen, and lunch shelter. The scope of work also included removal of 5 bungalows and upgrade of the electrical service.
|
Project Information
| Board Member |
Monica Garcia |
| Local Superintendent |
Dale Vigil |
| LA City Council |
Ed Reyes |
| Comm. Outreach |
Fernando Chavarria |
| Owner's Authorized Rep. (OAR) |
Christian Victor |
| Architect |
Friedman/Kimm Architects |
| General Contractor |
George C. Hopkins Construction Co., Inc. |
| 2-Semester Seats |
400 |
| New Classrooms |
16 |
| Site Acres |
N/A |
| Approximate Sq. Ft. |
23,962 |
| CHPS Score |
24 |
| Schools Relieved |
Existing School |
Schedule
| Pref. Site Designated |
Q1-2001 |
| DSA Approval |
Q2-2002 |
| NTP Construction |
Q2-2003 |
| School Occupancy |
Q4-2004 |
Cost
| Total Budget |
$ 10,207,950 |
Questions regarding this project?
Contact Community Outreach at 213-241-6523. |
|
Project last updated on 10/13/2011
|