Completed

Brooklyn ES - 2009-10 Prop 39, 56.41139
4620 Cesar Chavez Avenue, Los Angeles, CA 90022
Map and Directions

The Brooklyn ES campus will provide four classrooms that will accommodate approximately 80 charter students in grades K-1. The scope of work includes fencing, relocation of classrooms, rental of a temporary office, purchase of furniture and equipment, installation of a camera, intercom and buzzer at the charter school's entrance and ITD installation of a separate data and telephone network. Kipp Raices emy Charter School will reside at the Brooklyn ES campus for a single-year term with an expiration date of 6/30/10. Per BOE Report approved on 6/23/09.


Project Information
Board Member Bennett Kayser
Local Superintendent Robert A. Martinez
LA City Council N/A
Comm. Outreach
Owner's Authorized Rep. (OAR) Dale Smith
Architect TBD
General Contractor
2-Semester Seats N/A
New Classrooms N/A
Site Acres N/A
Approximate Sq. Ft. N/A
CHPS Score N/A
Schools Relieved N/A
Schedule
Pref. Site Designated Q2-2009
DSA Approval -
NTP Construction Q3-2009
School Occupancy Q3-2009
Cost
Total Budget $ 642,950
Project Attachments
No Attachments
Questions regarding this project?

Contact Community Outreach at 213-241-6523.
Project last updated on 10/13/2011